Kanakkuമലയാളം
HFW001-02-09 Beypore

Setting Up of Dialysis Centres-Feroke-Civil Work

Spent on this package so far

₹14.92 lakh

₹14,91,670

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Approval Created · How we group

Location

Money trail

Estimated amount
₹50,96,59,351Estimate of sub-project HFW001-01, shared by 148 contract packages
Expenditure reported · this package
₹14,91,670
Expenditure reported · all 148 packages
₹35,12,25,73468.9% of the estimated amount

Details

Project code
HFW001-02-09
Department
Health & Family Welfare
Constituency
BeyporeMLA: Shri P.A. Mohamed Riyas
Name as KIIFB publishes it
SETTING UP OF DIALYSIS CENTRES-FEROKE-CIVIL WORK

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project