TH Punalur - Furniture and Interior Outfits
Spent on this package so far
₹93.19 lakh
₹93,19,324
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: WBS Base One Approved · How we group
Money trail
- Estimated amount
- ₹68,18,03,600Estimate of sub-project HFW001-07, shared by 12 contract packages
- Expenditure reported · this package
- ₹93,19,324
- Expenditure reported · all 12 packages
- ₹62,14,03,26991.1% of the estimated amount
Details
- Project code
- HFW001-07-10
- Department
- Health & Family Welfare
- Executing agency
- INKEL Limited
- Constituency
- PunalurMLA: Shri P.S. Supal
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Punalur Taluk Hospital- Construction of New Block and Augmenting Basic Infrastructure - Package 1 ₹36.01 crore spent
- Taluk Hospital, Punalur - HVAC & Fire fighting works ₹7.74 crore spent
- Punalur Taluk Hospital - Construction of New Block - Electrical and ELV works. ₹7.07 crore spent
- Punalur Taluk Hospital - Medical Equipment - Through KMSCL ₹5.14 crore spent
- Punalur Taluk Hospital- Construction of New Block and Augmenting Basic Infrastructure - MGPS works ₹1.82 crore spent
- Punalur Taluk Hospital- Construction of New Block and Augmenting Basic Infrastructure - Lift works ₹1.74 crore spent
- Taluk Hospital Punalur- Development of External Infrastructure ₹1.36 crore spent
- Punalur Taluk Hospital- Construction of New Block and Augmenting Basic Infrastructure - Signages ₹32.2 lakh spent