Kanakkuമലയാളം
HFW002-19-01 Peravoor

The Development of Taluk Hospital, Peravoor in Kannur District (Civil Works,Electrical Works,Fire fighting and HVAC )

Estimated amount

₹40.86 crore

₹40,85,86,794 · ₹1.3 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹40,85,86,794₹40.86 crore
Expenditure reported
₹1,29,90,6873.2% of the estimated amount

Details

Project code
HFW002-19-01
Department
Health & Family Welfare
Executing agency
WAPCOS Limited
Constituency
PeravoorMLA: Shri Sunny Joseph

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Development of Taluk Hospital, Peravoor in Kannur District - Phase 1”.

Approved
₹40,85,86,794₹40.86 crore
Paid so far
₹4,75,01,16111.6% of the amount approved

This package

Work awarded
₹4.75 crorepaid
₹43.89 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress