This package
Work awarded₹9.17 crorepaid
₹11.78 croreapproved
₹11.21 crore
₹11,21,37,330 · ₹8.78 crore spent
KIIFB status: WBS Base One Approved · How we group
On KIIFB's project status page this belongs to “Development of TH Kothamangalam”.
Source: KIIFB project status (kiifb.org). Checked 30-09-2026. How we joined the two sources
The KIIFB dashboard does not publish these for this project: