Kanakkuമലയാളം
HFW005-03-02 Wadakkanchery

Development of GMC Thrissur - Construction of Mother & Child Block- Civil & MEP works

Estimated amount

₹279.19 crore

₹2,79,19,06,471 · ₹129.47 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹2,79,19,06,471₹279.19 crore
Expenditure reported
₹1,29,47,29,64046.4% of the estimated amount

Details

Project code
HFW005-03-02
Department
Health & Family Welfare
Executing agency
INKEL Limited
Constituency
WadakkancheryMLA: Shri Xavier Chittilappilly

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Development of Medical College, Thrissur - Mother & Child Block”.

Approved
₹2,79,19,06,471₹279.19 crore
Paid so far
₹1,53,82,22,68455.1% of the amount approved

This package

Work awarded
₹153.69 crorepaid
₹241.61 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…