Kanakkuമലയാളം
ITD003-01-01 Kazhakoottam

Construction of Executive International hostel block at DUK Campus in Technopark Phase IV, Thiruvananthapuram

Estimated amount

₹26.39 crore

₹26,39,14,368

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Created · How we group

Location

Money trail

Estimated amount
₹26,39,14,368₹26.39 crore
Expenditure reported
Not published

Details

Project code
ITD003-01-01
Department
Information Technology
Constituency
Kazhakoottam

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Construction of Executive International Hostel block for KUDSIT (DUK)”.

Approved
₹26,39,14,368₹26.39 crore
Paid so far
₹00% of the amount approved

This package

Work awarded
₹0paid
₹29.55 croreapproved

Source: KIIFB project status (kiifb.org). Checked 01-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress
  • Expenditure so far

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…