Kanakkuമലയാളം
LSG001-04-01 Kannur

Construction of Office Building for Kannur Municipal Corporation - Civil and Electrical Works

Estimated amount

₹37.83 crore

₹37,83,44,433 · ₹23.2 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹37,83,44,433₹37.83 crore
Expenditure reported
₹23,19,67,66961.3% of the estimated amount

Details

Project code
LSG001-04-01
Department
Local Self Government
Executing agency
IMPACT Kerala Ltd
Constituency
KannurMLA: Shri Ramachandran Kadannappalli

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Office Building of Kannur Municipal Corporation - Revised Estimate”.

Approved
₹37,83,44,433₹37.83 crore
Paid so far
₹25,49,30,46967.4% of the amount approved

This package

Work awarded
₹25.49 crorepaid
₹37.68 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…