Estimated amount

₹372.73 crore

₹3,72,73,00,000 · ₹267.55 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Money trail

Estimated amount
₹3,72,73,00,000₹372.73 crore
Expenditure reported
₹2,67,54,84,89471.8% of the estimated amount

Details

Project code
POW002-04-02
Department
Power
Executing agency
KSEBL Transgrid
Constituency
PerumbavoorMLA: Shri Eldose P. Kunnapillil
Constituency
AluvaMLA: Shri Anwar Sadath
Constituency
ThrikkakaraMLA: Smt. Uma Thomas
Constituency
Kunnathunad
Constituency
KothamangalamMLA: Shri Antony John
Constituency
DevikulamMLA: Shri A. Raja

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Kochi Lines Package”.

Approved
₹3,72,73,00,000₹372.73 crore
Paid so far
₹3,53,65,22,12194.9% of the amount approved

This package

Work started
₹279.75 crorepaid
₹279.79 croreapproved

Source: KIIFB project status (kiifb.org). Checked 30-09-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…