Kanakkuമലയാളം

Total of works

₹21.5 crore

₹21,50,00,000

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Koolimadu Bridge

Completed
100%Physical progress
99.1%Financial progress
Scheduled start05-03-2019
Scheduled completion04-05-2025
Implementing agency (SPV)
KRFB
Contract amount
₹16,40,71,762₹16.41 crore
Amount paid
₹16,26,42,644₹16.26 crore
Paid to contractor
₹15,07,34,970₹15.07 crore
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹21,50,00,000₹21.5 crore
Technical sanction (TS)
₹21,50,00,000₹21.5 crore
Tender amount
₹16,77,77,076₹16.78 crore
Letter of acceptance (LOA)
₹16,77,77,076₹16.78 crore
Current progress
All pier and pier cap completed. Land span in both side completed. All Girder casting completed but 3 number of girders damaged due to accident occour in site on 16/05/2022 . Three river span slab concreting completed. Prestressing girder work progressin

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹21,50,00,000₹21.5 crore

Details

Project code
PWD001-01-01
Department
Public Works
Constituency
Kunnamangalam

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…