Koolimadu Bridge
Completed100%Physical progress
99.1%Financial progress
Scheduled start05-03-2019
Scheduled completion04-05-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹16,40,71,762₹16.41 crore
- Amount paid
- ₹16,26,42,644₹16.26 crore
- Paid to contractor
- ₹15,07,34,970₹15.07 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹21,50,00,000₹21.5 crore
- Technical sanction (TS)
- ₹21,50,00,000₹21.5 crore
- Tender amount
- ₹16,77,77,076₹16.78 crore
- Letter of acceptance (LOA)
- ₹16,77,77,076₹16.78 crore
- Current progress
- All pier and pier cap completed. Land span in both side completed. All Girder casting completed but 3 number of girders damaged due to accident occour in site on 16/05/2022 . Three river span slab concreting completed. Prestressing girder work progressin