Total of works

₹23.96 crore

₹23,96,10,297

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Thorayikkadavu bridge

Scheduled completion was 04-01-2025. That was 636 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Thorayikkadavu bridge

In progress
38%Physical progress
24.4%Financial progress
Scheduled start05-07-2023
Scheduled completion04-01-2025
Implementing agency (SPV)
KRFB
Contract amount
₹22,91,69,862₹22.92 crore
Amount paid
₹5,58,98,433₹5.59 crore
Paid to contractor
₹5,23,45,546₹5.23 crore
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹23,96,10,297₹23.96 crore
Technical sanction (TS)
₹21,85,71,932₹21.86 crore
Tender amount
₹22,91,69,862₹22.92 crore
Current progress
Work tendered on 05/04/2022. Being single bidder qualified,work re-tendered on 23-04-2022.Financial bid opened on 05/05/2022 and LMR comparison under process. Tendering process in PDs office.LA in progress.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹23,96,10,297₹23.96 crore

Details

Project code
PWD001-02-02
Department
Public Works
Constituency
Koyilandy

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…