Thorayikkadavu bridge
In progress38%Physical progress
24.4%Financial progress
Scheduled start05-07-2023
Scheduled completion04-01-2025
- Contractor
- PMRConstruction Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹22,91,69,862₹22.92 crore
- Amount paid
- ₹5,58,98,433₹5.59 crore
- Paid to contractor
- ₹5,23,45,546₹5.23 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹23,96,10,297₹23.96 crore
- Technical sanction (TS)
- ₹21,85,71,932₹21.86 crore
- Tender amount
- ₹22,91,69,862₹22.92 crore
- Current progress
- Work tendered on 05/04/2022. Being single bidder qualified,work re-tendered on 23-04-2022.Financial bid opened on 05/05/2022 and LMR comparison under process. Tendering process in PDs office.LA in progress.