PWD001-09-05 Kochi

2016-17 Construction of Kumbalangi - Keltron-Keltron Ferry Bridge in Ernakulam District - Work Contract Package

Estimated amount

₹47.26 crore

₹47,26,45,400 · ₹6.2 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

Kumbalangi Keltron- Keltron ferry bridge

In progress
0%Physical progress
Not publishedFinancial progress
Scheduled start14-08-2025
Scheduled completion24-02-2027
Contractor
Rajuchacko
Implementing agency (SPV)
KRFB
Contract amount
₹41,71,02,413₹41.71 crore
Amount paid
Not published
Administrative sanction (AS)
₹45,00,00,000₹45 crore
Financial sanction (FS)
₹47,26,45,400₹47.26 crore
Technical sanction (TS)
₹43,06,00,000₹43.06 crore
Tender amount
₹41,71,02,413₹41.71 crore
Current progress
Land Acquisition- SIA study completed and draft report received on 27/01/2022. SIA Hearing conducted on 08/02/2022. Wet land clearance needed.Application given to Agricultural officer kumbalangi on 14/01/2022. site visited by agricultural officer for ins

Money trail

Estimated amount
₹47,26,45,400₹47.26 crore
Expenditure reported
₹6,19,71,56313.1% of the estimated amount

Details

Project code
PWD001-09-05
Department
Public Works
Constituency
KochiMLA: Shri K. J. Maxy
Name as KIIFB publishes it
KIIFB 2016-17 Construction of Kumbalangi - Keltron-Keltron Ferry Bridge in Ernakulam District - Work Contract Package

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Amount paid · Kumbalangi Keltron- Keltron ferry bridge

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026