Olampakkadavu bridge
In progress10.6%Physical progress
9.2%Financial progress
Scheduled start26-11-2024
Scheduled completion25-05-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹28,01,94,663₹28.02 crore
- Amount paid
- ₹2,57,80,125₹2.58 crore
- Paid to contractor
- ₹2,41,41,548₹2.41 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹43,94,03,172₹43.94 crore
- Technical sanction (TS)
- ₹25,47,35,800₹25.47 crore
- Tender amount
- ₹28,01,94,663₹28.02 crore
- Current progress
- The present contractor has completed his scope of work. The estimate for the balane work above pier cap is submitted on13/6/2022 for approval. Revenue A.S got vide G.O.(Rt)No.865/2020/RD Dated, Thiruvananthapuram, 27/02/2020 but due to the inclusion