Vatolli Bridge and reChekkupalam Bridge
In progress88%Physical progress
73.6%Financial progress
Scheduled start27-09-2023
Scheduled completion26-09-2024
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹3,39,98,614₹3.4 crore
- Amount paid
- ₹2,50,11,363₹2.5 crore
- Paid to contractor
- ₹2,34,21,649₹2.34 crore
- Administrative sanction (AS)
- ₹35,00,00,000₹35 crore
- Financial sanction (FS)
- ₹15,14,17,080₹15.14 crore
- Technical sanction (TS)
- ₹5,33,40,156₹5.33 crore
- Tender amount
- ₹3,39,98,614₹3.4 crore
- Current progress
- Vattoli Bridge- Bridge proper completed. Retaining wall work in A1 side completed. Chekku Bridge - Deck slab concrete completed (45m span). The work is terminated at the Risk and Cost of contractor as per order No.190/PWD001-15/PD/PMU-KRFB/68B/KNR/2018 D