Kondazhy - Kuthampully bridge
In progress97%Physical progress
67.4%Financial progress
Scheduled start16-10-2023
Scheduled completion16-10-2025
- Contractor
- T. A. Abdulrahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹28,12,27,452₹28.12 crore
- Amount paid
- ₹18,96,87,756₹18.97 crore
- Paid to contractor
- ₹17,92,38,836₹17.92 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹33,13,86,484₹33.14 crore
- Technical sanction (TS)
- ₹32,99,00,000₹32.99 crore
- Tender amount
- ₹28,16,72,190₹28.17 crore
- Current progress
- 11(1) notification published,Final amount details for LA received from Spl.Thahasildar (6,27,99,887/-) and the amount approved from PD and received the amount from CEO,KRFB transferred to Spl Tahsildar LA General Thrissur on 25/05/2022. Additional Amoun