Total of works

₹33.14 crore

₹33,13,86,484

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Kondazhy - Kuthampully bridge

Scheduled completion was 16-10-2025. That was 351 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kondazhy - Kuthampully bridge

In progress
97%Physical progress
67.4%Financial progress
Scheduled start16-10-2023
Scheduled completion16-10-2025
Implementing agency (SPV)
KRFB
Contract amount
₹28,12,27,452₹28.12 crore
Amount paid
₹18,96,87,756₹18.97 crore
Paid to contractor
₹17,92,38,836₹17.92 crore
Administrative sanction (AS)
₹15,00,00,000₹15 crore
Financial sanction (FS)
₹33,13,86,484₹33.14 crore
Technical sanction (TS)
₹32,99,00,000₹32.99 crore
Tender amount
₹28,16,72,190₹28.17 crore
Current progress
11(1) notification published,Final amount details for LA received from Spl.Thahasildar (6,27,99,887/-) and the amount approved from PD and received the amount from CEO,KRFB transferred to Spl Tahsildar LA General Thrissur on 25/05/2022. Additional Amoun

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹33,13,86,484₹33.14 crore

Details

Project code
PWD001-26-02
Department
Public Works
Constituency
Chelakkara

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026