Kumbichalkadavu Bridge
In progress95%Physical progress
85.7%Financial progress
Scheduled start24-02-2021
Scheduled completion30-09-2025
- Contractor
- M/s . SERMSInfrastructure Pvt. Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹24,80,81,019₹24.81 crore
- Amount paid
- ₹21,26,93,849₹21.27 crore
- Paid to contractor
- ₹19,91,12,864₹19.91 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹24,68,55,861₹24.69 crore
- Technical sanction (TS)
- ₹24,80,81,019₹24.81 crore
- Tender amount
- ₹21,14,10,238₹21.14 crore
- Current progress
- Work progress 16%. Plie construction - 10/48 done, Retaining Wall - 160/350 m done TOC upto 23.8.2022, extension required