Kanakkuമലയാളം

Total of works

₹25.7 crore

₹25,70,34,685

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Mukkattu Kadavu FathimaIsland bridge

Scheduled completion was 18-11-2024. That was 683 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Mukkattu Kadavu FathimaIsland bridge

In progress
98%Physical progress
82.2%Financial progress
Scheduled start26-06-2020
Scheduled completion18-11-2024
Implementing agency (SPV)
KRFB
Contract amount
₹21,71,09,241₹21.71 crore
Amount paid
₹17,84,62,373₹17.85 crore
Paid to contractor
₹16,68,24,670₹16.68 crore
Administrative sanction (AS)
₹15,00,00,000₹15 crore
Financial sanction (FS)
₹25,70,34,685₹25.7 crore
Technical sanction (TS)
₹40,44,73,098₹40.45 crore
Tender amount
₹19,96,84,527₹19.97 crore
Current progress
Fathima Island Bridge - 24 piles out of 24 completed. 8 out of 8 fender piles completed. 8 out of 8 pile caps completed. 5 out of 6 pier completed. 5 out of 6 Piers caps completed. 1 out of 2 Abutment walls completed. Concreting of 12 Girders out of

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹25,70,34,685₹25.7 crore

Details

Project code
PWD001-35-01
Department
Public Works
Constituency
Chavara

What we don't know yet

The dashboard publishes every field we check.