Mukkattu Kadavu FathimaIsland bridge
In progress98%Physical progress
82.2%Financial progress
Scheduled start26-06-2020
Scheduled completion18-11-2024
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹21,71,09,241₹21.71 crore
- Amount paid
- ₹17,84,62,373₹17.85 crore
- Paid to contractor
- ₹16,68,24,670₹16.68 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹25,70,34,685₹25.7 crore
- Technical sanction (TS)
- ₹40,44,73,098₹40.45 crore
- Tender amount
- ₹19,96,84,527₹19.97 crore
- Current progress
- Fathima Island Bridge - 24 piles out of 24 completed. 8 out of 8 fender piles completed. 8 out of 8 pile caps completed. 5 out of 6 pier completed. 5 out of 6 Piers caps completed. 1 out of 2 Abutment walls completed. Concreting of 12 Girders out of