Choolakkadavu Bridge
In progress21.5%Physical progress
13.8%Financial progress
Scheduled start14-10-2024
Scheduled completion13-04-2026
- Contractor
- PKSulpheeker Infrastructure LLP
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹28,50,43,778₹28.5 crore
- Amount paid
- ₹3,94,41,822₹3.94 crore
- Paid to contractor
- ₹3,69,34,910₹3.69 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹27,93,98,482₹27.94 crore
- Technical sanction (TS)
- ₹26,08,32,219₹26.08 crore
- Tender amount
- ₹28,50,43,778₹28.5 crore
- Current progress
- TS Estimate submitted including additional FS. . Contigency fund disbursed to LA Tahsildar .Stone laying works completed. LA in progress.