Overdue · Choolakkadavu Bridge

Scheduled completion was 13-04-2026. That was 172 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Choolakkadavu Bridge

In progress
21.5%Physical progress
13.8%Financial progress
Scheduled start14-10-2024
Scheduled completion13-04-2026
Implementing agency (SPV)
KRFB
Contract amount
₹28,50,43,778₹28.5 crore
Amount paid
₹3,94,41,822₹3.94 crore
Paid to contractor
₹3,69,34,910₹3.69 crore
Administrative sanction (AS)
₹20,00,00,000₹20 crore
Financial sanction (FS)
₹27,93,98,482₹27.94 crore
Technical sanction (TS)
₹26,08,32,219₹26.08 crore
Tender amount
₹28,50,43,778₹28.5 crore
Current progress
TS Estimate submitted including additional FS. . Contigency fund disbursed to LA Tahsildar .Stone laying works completed. LA in progress.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹27,93,98,482₹27.94 crore

Details

Project code
PWD001-42-02
Department
Public Works
Constituency
Payyannur

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…