Cherikkal Kottam bridge
In progress80.9%Physical progress
68%Financial progress
Scheduled start08-03-2023
Scheduled completion30-11-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹19,38,93,445₹19.39 crore
- Amount paid
- ₹13,19,34,897₹13.19 crore
- Paid to contractor
- ₹12,35,49,164₹12.35 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹23,11,77,134₹23.12 crore
- Technical sanction (TS)
- ₹19,38,93,445₹19.39 crore
- Tender amount
- ₹17,78,62,250₹17.79 crore
- Current progress
- Revenue AS received on 03/08/2021vide GO(Rt)No. 2500/2021/RD- Requisition submitted to District Collector on 09/08/21-Detailed estimate submitted for TS on 09/09/21 - LA initiated- 6(1) notification published- sanction for contingency charge accorded fr