Parayankadavu bridge
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Financial sanction (FS)
- ₹26,68,72,000₹26.69 crore
- Current progress
- Boundary stone Laying - Part TS has been obtained for the planting boundary stone .Agreement executed for the same on 02.03.2022. Boundary stone laying at edathuruthy side completed . Peg marking completed at Irinjalakkuda side. Due to native protest, wa