Kanakkuമലയാളം
PWD002-04 Kannur

8 Flyovers & 4 Underpasses

Total of works

₹130.87 crore

₹1,30,87,23,133

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

South Bazar Flyover

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
RBDCK
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹30,00,00,000₹30 crore
Financial sanction (FS)
₹1,30,87,23,133₹130.87 crore
Current progress
LA requisition submitted to District Collector and AS obtained from Revenue department on 04.01.2020. Stone planting and joint site inspection was completed. 4(1) published on 25.11.2020. 11(1) notification published as per Gazette No.1567 dated 20.05.20

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹1,30,87,23,133₹130.87 crore

Details

Project code
PWD002-04
Department
Public Works
Constituency
Kannur

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · South Bazar Flyover
  • Scheduled start and completion dates · South Bazar Flyover
  • Amount paid · South Bazar Flyover

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…