Melechova Flyover
In progress1%Physical progress
Not publishedFinancial progress
Scheduled start03-02-2025
Scheduled completion02-02-2027
- Implementing agency (SPV)
- RBDCK
- Contract amount
- ₹28,95,72,000₹28.96 crore
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹48,45,22,618₹48.45 crore
- Technical sanction (TS)
- ₹28,96,37,987₹28.96 crore
- Tender amount
- ₹28,95,72,000₹28.96 crore
- Letter of acceptance (LOA)
- ₹24,54,00,000₹24.54 crore
- Current progress
- NOC obtained from NHAI on 12.10.2021. The entire land (57.45Cents) has taken possession on 20.12.2021.RBDCK revised the estimate based on DSR 2018 and considered a lumpsum for utility shifting and submitted it to KIIFB for approval on 13.12.2021. But KII