Kanakkuമലയാളം

Estimated amount

Not published

No figure is published for this package alone.

Stage

Under appraisal

Status of the works, as KIIFB records it.

Location

Works (1)

Karunagappally Bypass road

Under appraisal
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Current progress
DPR Submitted and TAR received. The proposed bypass of length 12.9km to bypass NH 66 of length of 8.1 Km is not feasible as the procedures for widening NH 66 to four Lane is in progress. Also, all the stretches except last stretch of 5.5km is already res

Money trail

Estimated amount
Not published
Expenditure reported
Not published

Details

Project code
PWD003-07
Department
Public Works
Constituency
Karunagappally

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Karunagappally Bypass road
  • Scheduled start and completion dates · Karunagappally Bypass road
  • Amount paid · Karunagappally Bypass road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256