Karunagappally Bypass road
Under appraisal0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Current progress
- DPR Submitted and TAR received. The proposed bypass of length 12.9km to bypass NH 66 of length of 8.1 Km is not feasible as the procedures for widening NH 66 to four Lane is in progress. Also, all the stretches except last stretch of 5.5km is already res