Perambra Bypass
Completed100%Physical progress
98.8%Financial progress
Scheduled start08-07-2021
Scheduled completion14-08-2024
- Implementing agency (SPV)
- RBDCK
- Contract amount
- ₹20,58,73,762₹20.59 crore
- Amount paid
- ₹20,33,65,734₹20.34 crore
- Paid to contractor
- ₹18,48,72,818₹18.49 crore
- Administrative sanction (AS)
- ₹59,44,00,000₹59.44 crore
- Financial sanction (FS)
- ₹58,28,83,967₹58.29 crore
- Technical sanction (TS)
- ₹21,21,56,678₹21.22 crore
- Tender amount
- ₹22,05,60,951₹22.06 crore
- Letter of acceptance (LOA)
- ₹19,69,29,620₹19.69 crore
- Current progress
- Formation works 85% completed and 95% of drainage works completed. 100% Culvert works completed. 90% of DR wall works completed and remaining is in progress. 85% of GSB work completed and remaining is in progress. Retaining wall excavation works started.