Oradumpalam - Vylongara Bypass
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹1,29,00,000₹1.29 crore
- Financial sanction (FS)
- ₹16,09,46,735₹16.09 crore
- Current progress
- LA requisition submitted on 12.07.2018. AS for LA received on 19.06.2019. 6(1) Notification published on 07.10.2019. Due to protest from land owners stone planting obstructed, hence the project is put on hold. Now, letter received from new MLA Mankada o