Kechery-Akkikavu Bypass Road
Completed100%Physical progress
90.6%Financial progress
Scheduled start16-01-2024
Scheduled completion11-07-2025
- Contractor
- M/SBAABConstructions(I)Pvt. Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹45,68,04,117₹45.68 crore
- Amount paid
- ₹41,39,74,099₹41.4 crore
- Paid to contractor
- ₹38,76,37,150₹38.76 crore
- Financial sanction (FS)
- ₹54,61,68,782₹54.62 crore
- Technical sanction (TS)
- ₹45,68,04,118₹45.68 crore
- Tender amount
- ₹39,95,21,373₹39.95 crore
- Current progress
- Preliminary works : PED and Initial levels approved by EE-KRFB and forwarded to PD. CD works : In progress. 2 Culverts both sides and 6 slab one side concreting completed and 2 culvert raft works in progress.(Kechery to Pannithdam)