Kuttiyadi Bypass
In progress7%Physical progress
Not publishedFinancial progress
Scheduled start23-04-2025
Scheduled completion22-04-2026
- Contractor
- BAABConstructions(India)Pvt Ltd
- Implementing agency (SPV)
- RBDCK
- Contract amount
- ₹25,48,62,977₹25.49 crore
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹39,42,45,552₹39.42 crore
- Technical sanction (TS)
- ₹26,00,98,541₹26.01 crore
- Tender amount
- ₹25,48,62,977₹25.49 crore
- Letter of acceptance (LOA)
- ₹21,59,85,574₹21.6 crore
- Current progress
- Revised requisition submitted to DC, Kozhikode on 12.01.2021. As per the decision of District Collector revised alignment plan submitted to District Collector, Revenue AS obtained as per G.O.(Rt) No. 536/2012/RD dated 09.02.2021. Survey works for plant