PWD003-13-02 Kuttiady

Construction of Kuttiyadi Bypass

Estimated amount

₹39.42 crore

₹39,42,45,552 · ₹3.61 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Kuttiyadi Bypass

Scheduled completion was 22-04-2026. That was 163 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kuttiyadi Bypass

In progress
7%Physical progress
Not publishedFinancial progress
Scheduled start23-04-2025
Scheduled completion22-04-2026
Implementing agency (SPV)
RBDCK
Contract amount
₹25,48,62,977₹25.49 crore
Amount paid
Not published
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹39,42,45,552₹39.42 crore
Technical sanction (TS)
₹26,00,98,541₹26.01 crore
Tender amount
₹25,48,62,977₹25.49 crore
Letter of acceptance (LOA)
₹21,59,85,574₹21.6 crore
Current progress
Revised requisition submitted to DC, Kozhikode on 12.01.2021. As per the decision of District Collector revised alignment plan submitted to District Collector, Revenue AS obtained as per G.O.(Rt) No. 536/2012/RD dated 09.02.2021. Survey works for plant

Money trail

Estimated amount
₹39,42,45,552₹39.42 crore
Expenditure reported
₹3,61,48,4939.2% of the estimated amount

Details

Project code
PWD003-13-02
Department
Public Works
Constituency
Kuttiady

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Amount paid · Kuttiyadi Bypass

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026