Kanakkuമലയാളം

Estimated amount

Not published

No figure is published for this package alone.

Stage

Under appraisal

Status of the works, as KIIFB records it.

Location

Works (1)

Chathannoor-Edayadi road

Under appraisal
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹1,00,00,00,000₹100 crore
Current progress
DPR submitted and TAR received. Additional details called for from Design wing has been received from RIQCL. Received Details were forwarded for onward submission to CE Design wing for preparing DPR as per TAR & DPR recieved . Utility shifting estimate

Money trail

Estimated amount
Not published
Expenditure reported
Not published

Details

Project code
PWD004-09
Department
Public Works
Constituency
Chathannoor

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Chathannoor-Edayadi road
  • Scheduled start and completion dates · Chathannoor-Edayadi road
  • Amount paid · Chathannoor-Edayadi road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…