Kaithapoyil - Kodanchery Road
In progress90%Physical progress
38.6%Financial progress
Scheduled start11-11-2022
Scheduled completion10-11-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹51,94,44,698₹51.94 crore
- Amount paid
- ₹20,87,65,978₹20.88 crore
- Paid to contractor
- ₹19,54,96,919₹19.55 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹90,08,70,534₹90.09 crore
- Technical sanction (TS)
- ₹51,64,30,080₹51.64 crore
- Tender amount
- ₹54,09,08,861₹54.09 crore
- Current progress
- GSB completed 16 km .GSB partially completed 2 km.WMM completed 12 km.WMM partially completed 2 km.DBM completed 11.200 km. 68 nos of culvert completed . 2 culvert at 9/500 & 20/900 ongoing1 nos to be completed at 5/060 1 nos extension of culvert (Mura