Mannur - Ponjassery Road
Completed100%Physical progress
96.9%Financial progress
Scheduled start31-03-2023
Scheduled completion31-03-2025
- Contractor
- Rajesh Mathewand Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹10,86,46,355₹10.86 crore
- Amount paid
- ₹10,53,23,715₹10.53 crore
- Paid to contractor
- ₹9,91,64,983₹9.92 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹26,50,64,539₹26.51 crore
- Technical sanction (TS)
- ₹9,99,49,000₹9.99 crore
- Tender amount
- ₹10,92,93,942₹10.93 crore
- Current progress
- " The work taken over from Roads Division,Muvattupuzha on 28/10/2021.Before taking over itself work had been standstill.Hence first notice of terimnation issued on 04/11/2021. 2.94km DBM completed on 11/2/2022.Again contractor made the work standstill