Mannur - Ponjassery Road
Approved100%Physical progress
Not publishedFinancial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹26,50,64,539₹26.51 crore
- Technical sanction (TS)
- ₹2,00,00,000₹2 crore
- Tender amount
- ₹2,13,87,154₹2.14 crore
- Current progress
- " The work taken over from Roads Division,Muvattupuzha on 28/10/2021.Before taking over itself work had been standstill.Hence first notice of terimnation issued on 04/11/2021. 2.94km DBM completed on 11/2/2022.Again contractor made the work standstill