Kanakkuമലയാളം

Total of works

₹14.45 crore

₹14,45,29,868

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Akkikavu - Kadangode Erumapetty road

Completed
100%Physical progress
100%Financial progress
Scheduled start01-02-2019
Scheduled completion30-06-2025
Contractor
K. M. Ameer
Implementing agency (SPV)
KRFB
Contract amount
₹11,07,77,447₹11.08 crore
Amount paid
₹11,07,45,766₹11.07 crore
Paid to contractor
₹10,41,76,797₹10.42 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹14,45,29,868₹14.45 crore
Technical sanction (TS)
₹11,07,77,447₹11.08 crore
Tender amount
₹10,10,28,060₹10.1 crore
Letter of acceptance (LOA)
₹10,10,28,060₹10.1 crore
Current progress
DBM Completed - 9.34 Km. BC: Completed in 9.00 km out of 9.34 km. (700 m one side left to be completed) CD works: Completed (29 culverts and drains(3206m),Retaining wall - 316m

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹14,45,29,868₹14.45 crore

Details

Project code
PWD004-109-01
Department
Public Works
Constituency
Kunnamkulam

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…