Akkikavu - Kadangode Erumapetty road
Completed100%Physical progress
100%Financial progress
Scheduled start01-02-2019
Scheduled completion30-06-2025
- Contractor
- K. M. Ameer
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹11,07,77,447₹11.08 crore
- Amount paid
- ₹11,07,45,766₹11.07 crore
- Paid to contractor
- ₹10,41,76,797₹10.42 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹14,45,29,868₹14.45 crore
- Technical sanction (TS)
- ₹11,07,77,447₹11.08 crore
- Tender amount
- ₹10,10,28,060₹10.1 crore
- Letter of acceptance (LOA)
- ₹10,10,28,060₹10.1 crore
- Current progress
- DBM Completed - 9.34 Km. BC: Completed in 9.00 km out of 9.34 km. (700 m one side left to be completed) CD works: Completed (29 culverts and drains(3206m),Retaining wall - 316m