Kothamangalam Perumbankuthu road
Completed100%Physical progress
99.2%Financial progress
Scheduled start31-01-2019
Scheduled completion14-07-2025
- Contractor
- K. I. Paulose
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹20,42,20,192₹20.42 crore
- Amount paid
- ₹20,26,81,731₹20.27 crore
- Paid to contractor
- ₹18,93,26,784₹18.93 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹22,09,25,192₹22.09 crore
- Technical sanction (TS)
- ₹20,42,20,192₹20.42 crore
- Tender amount
- ₹18,22,98,124₹18.23 crore
- Letter of acceptance (LOA)
- ₹18,22,98,124₹18.23 crore
- Current progress
- This work is now under the charge of EE, PWD Roads Division Muvattupuzha.BC finished. Line mariking in progress. Physical progress - 96%.