Plamudy Kottappady Road
Approved0%Physical progress
Not publishedFinancial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹22,66,00,000₹22.66 crore
- Technical sanction (TS)
- ₹12,94,00,000₹12.94 crore
- Current progress
- Work has taken over from Roads Division Muvattupuzha on 21/10/2021.. Surface damages and settlements were there on the road surface in DBM, which was executed under PWD Roads Division,Muvattupuzha. Based on the request from this office, KIIFB team visite