Nadathara - Moorkanikkara - Kannara Road
Approved3%Physical progress
Not publishedFinancial progress
Scheduled start29-11-2024
Scheduled completion29-05-2026
- Contractor
- M/s EKKInfrastructure Limited
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹38,07,27,760₹38.07 crore
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹50,12,30,000₹50.12 crore
- Technical sanction (TS)
- ₹50,12,30,000₹50.12 crore
- Tender amount
- ₹38,07,27,760₹38.07 crore
- Current progress
- FS- Obtained FDR -As ROW of 10m is not available for the entire lengt