Edakunny Road
Completed100%Physical progress
87.4%Financial progress
Scheduled start01-02-2019
Scheduled completion06-11-2025
- Contractor
- K. M. Ameer
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹28,18,23,755₹28.18 crore
- Amount paid
- ₹24,63,72,231₹24.64 crore
- Paid to contractor
- ₹23,07,72,975₹23.08 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹32,98,00,000₹32.98 crore
- Technical sanction (TS)
- ₹32,98,00,000₹32.98 crore
- Tender amount
- ₹28,55,80,961₹28.56 crore
- Letter of acceptance (LOA)
- ₹28,55,80,961₹28.56 crore
- Current progress
- Road work Paving Tile completed- 180m (0/000-0/180 -Mannuthy Center ) DBM completed -7.1km. 0/180 - 2/600 (Mannuthy to Nadathara Center ) 2/880 - 7/410 (Nadathara NH to Ollur centre) WMM completed-7.30 km. GSB completed -7.30km CD works -