Chalakudy Anamala Road
Completed100%Physical progress
84.9%Financial progress
Scheduled start09-10-2020
Scheduled completion31-03-2025
- Contractor
- RPPInfra Projects Limited
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹25,38,83,128₹25.39 crore
- Amount paid
- ₹21,55,82,406₹21.56 crore
- Paid to contractor
- ₹20,17,80,099₹20.18 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹27,99,76,654₹28 crore
- Technical sanction (TS)
- ₹25,38,83,128₹25.39 crore
- Tender amount
- ₹22,79,49,592₹22.79 crore
- Letter of acceptance (LOA)
- ₹22,79,49,592₹22.79 crore
- Current progress
- Preliminary works Initial Level survey completed TBM errected at site. Project execution documents uploaded to PFMS portal. Initial setting out and alignment fixation is over. Road work DR Masonry for protection wall is in progress. Drain and pipe culver