Kuppam- Chudala Road
In progress100%Physical progress
93%Financial progress
Scheduled start09-10-2018
Scheduled completion31-07-2023
- Contractor
- P. K. Sulphiker
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹52,66,61,443₹52.67 crore
- Amount paid
- ₹48,99,31,691₹48.99 crore
- Paid to contractor
- ₹45,56,42,436₹45.56 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹62,08,35,855₹62.08 crore
- Technical sanction (TS)
- ₹54,21,17,527₹54.21 crore
- Tender amount
- ₹52,66,61,443₹52.67 crore
- Letter of acceptance (LOA)
- ₹52,66,61,443₹52.67 crore
- Current progress
- Work is in progress by the new company,P.K Sulphikker LLP.Agreement with this company has been executed on 27-01-2022. 89% work completed. GSB,WMM&DBM completed.Drainage and side protection work in progress.