PWD004-122-02 Udma

Improvements to Thekkil - Alatty road - Contract work

Spent on this package so far

₹65.12 crore

₹65,12,09,948

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

Thekkil-Alatty Road

Completed
100%Physical progress
99.5%Financial progress
Scheduled start24-07-2018
Scheduled completion31-10-2023
Implementing agency (SPV)
KRFB
Contract amount
₹68,79,46,014₹68.79 crore
Amount paid
₹68,48,33,852₹68.48 crore
Paid to contractor
₹63,43,50,256₹63.44 crore
Financial sanction (FS)
₹82,61,82,298₹82.62 crore
Technical sanction (TS)
₹77,90,98,095₹77.91 crore
Tender amount
₹62,93,99,280₹62.94 crore
Letter of acceptance (LOA)
₹62,93,99,280₹62.94 crore
Current progress
Work completed. Total length of project is 34.66 Km. In this works completed for 33.32 Km. Work could not be taken up for 1.34 Km due to pending court cases and for want of construction of bridge which is not part of original agreement. Work foreclosed

Money trail

Estimated amount
₹82,61,82,298Estimate of sub-project PWD004-120, shared by 2 contract packages
Expenditure reported · this package
₹65,12,09,948
Expenditure reported · all 2 packages
₹65,12,09,94878.8% of the estimated amount

Details

Project code
PWD004-122-02
Department
Public Works
Constituency
Udma

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project