Thekkil-Alatty Road
Completed100%Physical progress
99.5%Financial progress
Scheduled start24-07-2018
Scheduled completion31-10-2023
- Contractor
- ASSMASConstructions Pvt. Ltd.
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹68,79,46,014₹68.79 crore
- Amount paid
- ₹68,48,33,852₹68.48 crore
- Paid to contractor
- ₹63,43,50,256₹63.44 crore
- Financial sanction (FS)
- ₹82,61,82,298₹82.62 crore
- Technical sanction (TS)
- ₹77,90,98,095₹77.91 crore
- Tender amount
- ₹62,93,99,280₹62.94 crore
- Letter of acceptance (LOA)
- ₹62,93,99,280₹62.94 crore
- Current progress
- Work completed. Total length of project is 34.66 Km. In this works completed for 33.32 Km. Work could not be taken up for 1.34 Km due to pending court cases and for want of construction of bridge which is not part of original agreement. Work foreclosed