Balance work in Thekkil-Alatty Road- Construction of Pulinchal bridge and Junction Improvements- Contract Package.
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Project Created · How we group
Location
The location KIIFB records lies outside this map.
Money trail
- Estimated amount
- ₹82,61,82,298Estimate of sub-project PWD004-120, shared by 2 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 2 packages
- ₹65,12,09,94878.8% of the estimated amount
Details
- Project code
- PWD004-122-05
- Department
- Public Works
- Executing agency
- Kerala Road Fund Board (KRFB)
- Constituency
- Udma
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Improvements to Thekkil - Alatty road - Contract work ₹65.12 crore spent