Petta- Anayara-Oruvathilkotta Road
In progress32.6%Physical progress
24.4%Financial progress
Scheduled start18-02-2024
Scheduled completion17-02-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹52,85,18,009₹52.85 crore
- Amount paid
- ₹12,89,64,522₹12.9 crore
- Paid to contractor
- ₹12,07,67,604₹12.08 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹1,60,55,09,343₹160.55 crore
- Technical sanction (TS)
- ₹38,51,89,687₹38.52 crore
- Tender amount
- ₹52,85,18,009₹52.85 crore
- Current progress
- Valuation completed, Revenue survey completed. As requested by the Revenue authoirity proposal for remitting Rs. 100.68 Crore (LA Cost) remitted towards the charge for land acquisition LA will be completed by the 2nd week of October. TS estimate under pr