Kottarakara ring road
Terminated70.2%Physical progress
84.1%Financial progress
Scheduled start23-04-2018
Scheduled completion31-12-2025
- Contractor
- M/s Kavumkal Road Builders
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹15,44,38,246₹15.44 crore
- Amount paid
- ₹12,99,30,935₹12.99 crore
- Paid to contractor
- ₹12,01,86,103₹12.02 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹23,45,56,687₹23.46 crore
- Technical sanction (TS)
- ₹18,17,11,494₹18.17 crore
- Tender amount
- ₹16,60,48,076₹16.6 crore
- Letter of acceptance (LOA)
- ₹16,60,48,076₹16.6 crore
- Current progress
- 13.225Km BC completed. 8.085Km BM completed. 250m WMM completed. The project was suspended by KIIFB and now suspension is revoked. Approval of RE pending with KIIFB. KWA utility shifting completed. KSEB utility shifting nearing completion.