Kanakkuമലയാളം

Total of works

₹23.46 crore

₹23,45,56,687

Stage

Terminated

Status of the works, as KIIFB records it.

Location

Works (1)

Kottarakara ring road

Terminated
70.2%Physical progress
84.1%Financial progress
Scheduled start23-04-2018
Scheduled completion31-12-2025
Implementing agency (SPV)
KRFB
Contract amount
₹15,44,38,246₹15.44 crore
Amount paid
₹12,99,30,935₹12.99 crore
Paid to contractor
₹12,01,86,103₹12.02 crore
Administrative sanction (AS)
₹15,00,00,000₹15 crore
Financial sanction (FS)
₹23,45,56,687₹23.46 crore
Technical sanction (TS)
₹18,17,11,494₹18.17 crore
Tender amount
₹16,60,48,076₹16.6 crore
Letter of acceptance (LOA)
₹16,60,48,076₹16.6 crore
Current progress
13.225Km BC completed. 8.085Km BM completed. 250m WMM completed. The project was suspended by KIIFB and now suspension is revoked. Approval of RE pending with KIIFB. KWA utility shifting completed. KSEB utility shifting nearing completion.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹23,45,56,687₹23.46 crore

Details

Project code
PWD004-13-01
Department
Public Works
Constituency
Kottarakkara

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…