Kanakkuമലയാളം

Total of works

₹41.21 crore

₹41,21,05,727

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Karma Bridges

Completed
100%Physical progress
89.3%Financial progress
Scheduled start26-06-2020
Scheduled completion31-05-2023
Implementing agency (SPV)
KRFB
Contract amount
₹40,64,28,412₹40.64 crore
Amount paid
₹36,30,32,068₹36.3 crore
Paid to contractor
₹33,90,57,672₹33.91 crore
Administrative sanction (AS)
₹30,00,00,000₹30 crore
Financial sanction (FS)
₹41,21,05,727₹41.21 crore
Technical sanction (TS)
₹37,48,00,000₹37.48 crore
Tender amount
₹40,64,28,412₹40.64 crore
Letter of acceptance (LOA)
₹40,64,28,412₹40.64 crore
Current progress
Bridge Proper Bridge proper work completed Approach road Ponnani side - Construction of RCC Retaining wall work in progress. Chamravattam side - Request submitted to Irrigation Dept. for getting the NOC for constructing the approach road on Karma side

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹41,21,05,727₹41.21 crore

Details

Project code
PWD004-135-01
Department
Public Works
Constituency
Thavanur,Ponnani

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026