Karma Bridges
Completed100%Physical progress
89.3%Financial progress
Scheduled start26-06-2020
Scheduled completion31-05-2023
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹40,64,28,412₹40.64 crore
- Amount paid
- ₹36,30,32,068₹36.3 crore
- Paid to contractor
- ₹33,90,57,672₹33.91 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹41,21,05,727₹41.21 crore
- Technical sanction (TS)
- ₹37,48,00,000₹37.48 crore
- Tender amount
- ₹40,64,28,412₹40.64 crore
- Letter of acceptance (LOA)
- ₹40,64,28,412₹40.64 crore
- Current progress
- Bridge Proper Bridge proper work completed Approach road Ponnani side - Construction of RCC Retaining wall work in progress. Chamravattam side - Request submitted to Irrigation Dept. for getting the NOC for constructing the approach road on Karma side