Estimated amount

Not published

No figure is published for this package alone.

Stage

Under appraisal

Status of the works, as KIIFB records it.

Location

Works (1)

Alakkode - Kappimala road

Under appraisal
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹15,00,00,000₹15 crore
Current progress
DPR submitted to KIIFB for FS for 46.11 crore. Categorised as Low volume road-Decision was pending with KIIFB for one year- Based on ED, KIIFB visit on 20-09-2021 KIIFB suggested to drop the project vide letter dated 25-10-21

Money trail

Estimated amount
Not published
Expenditure reported
Not published

Details

Project code
PWD004-136
Department
Public Works
Constituency
Irikkur

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Alakkode - Kappimala road
  • Scheduled start and completion dates · Alakkode - Kappimala road
  • Amount paid · Alakkode - Kappimala road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026