Alakkode - Kappimala road
Under appraisal0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Current progress
- DPR submitted to KIIFB for FS for 46.11 crore. Categorised as Low volume road-Decision was pending with KIIFB for one year- Based on ED, KIIFB visit on 20-09-2021 KIIFB suggested to drop the project vide letter dated 25-10-21