Keezhmadam-Kunnothparamba road
In progress2%Physical progress
Not publishedFinancial progress
Scheduled start18-04-2025
Scheduled completion17-04-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹21,39,28,095₹21.39 crore
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹37,62,18,405₹37.62 crore
- Technical sanction (TS)
- ₹19,44,90,009₹19.45 crore
- Tender amount
- ₹21,39,28,095₹21.39 crore
- Current progress
- 64 % work completed(7.71 km BC completed,8.4 km Drainage completed,12 culverts out of 23 nos completed). Work stopped due to non availability of free surrender land. A Project Risk Based Intervention meeting was conducted by Senior Project Examiner KIIF