Punalur Town Roads
Completed100%Physical progress
84.2%Financial progress
Scheduled start27-02-2018
Scheduled completion30-08-2022
- Contractor
- M/s Palathra Constructions
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹13,28,93,986₹13.29 crore
- Amount paid
- ₹11,19,25,786₹11.19 crore
- Paid to contractor
- ₹10,35,31,341₹10.35 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹15,15,00,000₹15.15 crore
- Technical sanction (TS)
- ₹15,15,00,000₹15.15 crore
- Tender amount
- ₹13,28,93,986₹13.29 crore
- Letter of acceptance (LOA)
- ₹13,28,93,986₹13.29 crore
- Current progress
- Work completed as per schedule quantities . Revised estimate is submitted to KIIFB on 15.03.2022 for approval.