Sreekrishnapuram- Chethallur road
Completed100%Physical progress
85.3%Financial progress
Scheduled start05-01-2022
Scheduled completion18-10-2025
- Contractor
- M/s PMRConstruction Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹27,72,30,019₹27.72 crore
- Amount paid
- ₹23,65,97,703₹23.66 crore
- Paid to contractor
- ₹22,15,59,669₹22.16 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹54,71,71,994₹54.72 crore
- Technical sanction (TS)
- ₹54,71,71,994₹54.72 crore
- Tender amount
- ₹24,26,73,033₹24.27 crore
- Current progress
- Work started for first phase from 0/000 to 7/700.Widening in progress. Construction of compound wall ongoing. Culvert work and retaining wall work started.Total project completion is 10%. TS estimate submitted for approval for the 2nd Phase of work from