Kanakkuമലയാളം

Improvements to Sreekrishnapuram Muriyamkanni Chethallur Road 0/000 12/450 in Palakkad District - Phase 1 - km 0/000 to 7/700 - Contract

Spent on this package so far

₹22.66 crore

₹22,65,72,332

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

Sreekrishnapuram- Chethallur road

Completed
100%Physical progress
85.3%Financial progress
Scheduled start05-01-2022
Scheduled completion18-10-2025
Implementing agency (SPV)
KRFB
Contract amount
₹27,72,30,019₹27.72 crore
Amount paid
₹23,65,97,703₹23.66 crore
Paid to contractor
₹22,15,59,669₹22.16 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹54,71,71,994₹54.72 crore
Technical sanction (TS)
₹54,71,71,994₹54.72 crore
Tender amount
₹24,26,73,033₹24.27 crore
Current progress
Work started for first phase from 0/000 to 7/700.Widening in progress. Construction of compound wall ongoing. Culvert work and retaining wall work started.Total project completion is 10%. TS estimate submitted for approval for the 2nd Phase of work from

Money trail

Estimated amount
₹54,71,71,994Estimate of sub-project PWD004-143, shared by 2 contract packages
Expenditure reported · this package
₹22,65,72,332
Expenditure reported · all 2 packages
₹25,04,12,36445.8% of the estimated amount

Details

Project code
PWD004-143-01
Department
Public Works
Constituency
ShornurMLA: Shri P. Mammikutty
Constituency
Ottappalam
Constituency
Shornur,Ottappalam
Name as KIIFB publishes it
IMPROVEMENTS TO SREEKRISHNAPURAM MURIYAMKANNI CHETHALLUR ROAD 0/000 12/450 IN PALAKKAD DISTRICT - Phase 1 - km 0/000 to 7/700 - Contract

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements to Sreekrishnapuram Muriyamkanni Chethallur Road 0/000 12/450 in Palakkad District”. The figures below are for that whole project, not this package alone.

Approved
₹54,71,71,994₹54.72 crore
Paid so far
₹40,83,71,66874.6% of the amount approved

This package

Work awarded
₹23.66 crorepaid
₹27.72 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project