Sreekrishnapuram- Chethallur road
In progress1%Physical progress
Not publishedFinancial progress
Scheduled start15-07-2025
Scheduled completion14-01-2027
- Contractor
- M/s Malabar Tech
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹19,29,72,400₹19.3 crore
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹54,71,71,994₹54.72 crore
- Technical sanction (TS)
- ₹23,11,50,000₹23.12 crore
- Tender amount
- ₹19,29,72,400₹19.3 crore
- Current progress
- Work started for first phase from 0/000 to 7/700.Widening in progress. Construction of compound wall ongoing. Culvert work and retaining wall work started.Total project completion is 10%. TS estimate submitted for approval for the 2nd Phase of work from