Mannur-Chaliyam Road
Completed100%Physical progress
95.4%Financial progress
Scheduled start24-07-2019
Scheduled completion23-04-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹49,06,35,398₹49.06 crore
- Amount paid
- ₹46,78,30,622₹46.78 crore
- Paid to contractor
- ₹43,27,94,092₹43.28 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹51,36,50,499₹51.37 crore
- Technical sanction (TS)
- ₹49,06,35,398₹49.06 crore
- Tender amount
- ₹48,55,56,312₹48.56 crore
- Letter of acceptance (LOA)
- ₹48,55,56,312₹48.56 crore
- Current progress
- GSB/WMM work completed for a length of 7200m. Drain completed for a total length of 14830 m. DR completed for a total length of 4866m DBM completed for a total length of 7600m. BC completed upto a length of 7500m. CD works completed. Enrochment eviction