Karaparamba - Paroppodi road
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹20,00,30,000₹20 crore
- Current progress
- Rs. 20.0 Crore sanctioned for LA. Alignment plan approved on 29.09.21 by CE roads. Request for G O for LA submitted on 05.01.2022. Public protest in boundary stone laying.GO obtained and requistion submitted.LAO appointed and 6(1) obtained. Boundary sto