Pangodu - Kadakkal - Chingeli Road
Completed100%Physical progress
99.9%Financial progress
Scheduled start12-05-2023
Scheduled completion05-05-2025
- Contractor
- Athajudeen
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹4,20,20,698₹4.2 crore
- Amount paid
- ₹4,19,83,430₹4.2 crore
- Paid to contractor
- ₹3,94,42,322₹3.94 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹27,80,00,000₹27.8 crore
- Technical sanction (TS)
- ₹4,88,40,000₹4.88 crore
- Tender amount
- ₹5,34,30,294₹5.34 crore
- Current progress
- DBM & BC Completed.. contractor has requested to terminate the contract. Design of Mathira bridge received from PWD Design wing. As per proceedings of the Project director, KRFB, vide Order